Required team for the construction of wooden baths. Brigade of builders of houses from a bar

Despite the technological progress due to the development of the industrial sector, wooden houses remain popular to this day. Many different materials are used to build houses:

  • brick
  • foam blocks
  • reinforced concrete
  • granite or marble
  • wood

Historically, it so happened that it was the construction of houses from timber or simple logs that was the first and most massive. This is due to various factors, such as the availability wooden materials. However, it is a mistake to believe that the construction of wooden houses is a simple process performed by workers without special knowledge. This is not true. The construction of a wooden house requires a thorough approach, including the customer is advised to carefully select the workers.

Why should you hire professionals?

The complexity of building wooden houses is determined by the following factors:

These and other factors explain the expediency of applying for the services of working teams for the construction of wooden houses.

How to find a team for the construction of wooden houses

Before turning to workers who are ready to build a wooden house professionally and inexpensively, a number of actions must be taken.

First you need to decide on the material from which the customer wants to build a private house. A tree is great for this, its advantages boil down to the following:

  • Environmental friendliness. Wood - natural material, this is one of the reasons that logs are so often used and big companies, and private teams for the construction of wooden houses
  • thermal insulation properties. Modern processing allows the tree to acquire amazing character traits: The house is cool in summer and warm in winter. This is possible thanks to the special processing of logs.
  • Reliability. Thanks to special impregnation, the tree from which the house is built does not burn - it is protected from fire
  • Durability. Wood is one of the most practical and durable materials that are used to build houses.

To hire the right company for the construction of a wooden house, you can use several options. For example, using the Yudu service, you can find out the prices for the services of brigades for the construction of wooden houses, in particular, log cabins. Here you can also get acquainted with the price list of the contractor, compare prices and, finally, hire the right work team. You can get acquainted with the price list of contractors and order their services directly on the site by opening a new task. With the help of the Yudu service, you can find an experienced team ready to perform the work of erecting a log house professionally and inexpensively.

AT recent times services for the construction of baths and saunas are becoming more and more relevant. This is not surprising, because baths, characterized by clean steam and hot air, are a great way to relax.

Today, many, in order to take a steam bath and relax, resort to the services of commercial establishments providing bath services. However, this is quite inconvenient for a number of reasons:

  • Long way to the relevant organization providing bath services
  • The need to spend a certain amount of time in line
  • Pre-registration for the provision of relevant services

Because of all these shortcomings, many people have a desire to build their own bath. Obviously, the construction of baths is a complex process that has a number of features that are known only to experienced professionals. Therefore, in order to build a bath or sauna, you need to find a good construction team.

How to hire a team to build a bath

Today there are many different private teams for the construction of baths and saunas. Many of them are newly formed and have little experience, so the choice of a contractor should be considered carefully. With this approach, the client will be able to find workers who are ready to carry out all the necessary services professionally and inexpensively. In general, when looking for private teams involved in the construction of baths and saunas, you need to pay attention to the following points:

  • Experience in providing construction services the relevant work team
  • Valuations of the brigades, carrying out the construction of baths and saunas. It is recommended to carefully study the price list, compare prices for the services of private teams
  • Construction team experience various materials. Many companies work with timber and foam blocks, however, at the request of the client, it is possible to use other materials

From what the work crews carry out the construction of baths

The two most commonly used building materials are:

  • Beam, tree. Baths made in this way remain the most common today. Log cabins are eco-friendly. In addition, it is log cabins made of logs that convey the atmosphere of a classic bath. The logs are usually held together and sealed with resin.
  • Foam blocks. Often used to build saunas. Foam blocks have excellent thermal insulation, which allows you to save temperature regime long time

The choice of building material depends on the goals pursued by the customer, on financial position client and other factors. Professional companies, as a rule, offer a wide range of building materials from which you can build a bath or sauna.

Check out the price list construction companies, you can compare their prices and hire suitable workers who are ready to do the job professionally and inexpensively with the help of a specialized Yudu service.

Looking for carpenters for construction log house 10.00x10.00 from sawn timber of natural humidity with a section of 200x200
The forest was brought from Arkhangelsk, selected Pine.

1st stage of work (tape foundation 40 cm wide + 3 rows of bricks) Already done!

Required:
1. Assembly of a log house 10.00x10.00 meters, two floors from a bar 200x200 mm. (the total volume of wood according to the project is about 90 m3). Bevels need to be removed. External walls along the perimeter, the chamfer is removed only from the upper edge. Internal walls and partitions on both sides, top and bottom.
2. The height of the first floor is 3.20 (16 pieces of timber), the second half-attic floor - (8 pieces of timber). An attic is not planned. The height of the second half-mansard house under the ridge. The total height of the house from the foundation to the ridge is 7.43 m. According to the project
3. The roof is gabled, with two gables.
4. The main walls of the house with a perimeter size of 10.00x10.00 - with the rise of the walls of the second floor by 1.60 meters, are made of timber 200x200 mm. Installation of windows and doors at this stage is not planned, only rough openings for ventilation inside the house. The bars are placed on a foundation 40 cm wide. Closer to the inner edge, i.e. there remains a place for finishing the outside with brick in the future.
5. Internal walls on the first floor and on the second floor are made of timber 200x200 mm. All walls of the second floor rise under the ridge of the roof (i.e. without forming an attic).
6. Larch lining board must be treated with an antiseptic. Sexual and ceiling beams made of timber 100x200 mm every 0.58-0.59 meters (per edge) (9 pieces per room, less according to the project). The floor joists must be sawn (embedded) into the 1st crown.
7. The pediments of the second floor at the base of 10.40 meters and a height of 3.00 meters are made of timber 200x200 mm. On a rectangular bay window, a separate pediment at the base of 5.20 meters and a height of 1.50 meters is made of timber 200x200 mm with a separate gable roof(one slope in the same plane with the main roof).
8. truss structure(REQUIRES Sliding Rafter Device). Removal of rafter beams by more than half a meter. (0.7-0.8)
9. The truss structure is made of a board 50x200 mm every 0.60 meters.
10. The roof lathing should be done as follows:
A) Wind-, waterproofing film
B) Control grid (50x50 mm)
C) The roof lathing is made of a board 25x150 (with a step under the metal tile profile “Country” Grand Line).
D) All roof elements must be treated in two layers with fire protection (which is used in sub-zero temperatures).
D) Roof roofing roofing felt.
11. On the first and second floors inside the house, rough floors were made from boards 25x150 mm along cranial bars 50x50 mm. (1st floor with antiseptic)
12. Waterproofing was made between the foundation and the lower crown of the house (1 layer of glass insulation already lies). It is necessary to lay 2 layers of roofing material.
13. Between the crowns of the beam - an antiseptic and only then an interventional insulation (jute 20 cm.). In internal partitions antiseptic is not required. Antiseptic treatment between the crowns of the timber is required only for the outer walls.
14. Docking of timber in the corners, the junction of internal walls, along the length, is carried out "in a half-dovetail" (warm corner) or another variant of the joint in a warm corner.
15. Assembly of a house from a bar is carried out on wooden dowels only, step 1 meter, in front of openings 10-20 cm.
16. Lining board, 1st lower crown of the house, beams and boards of the 1st floor must be treated with an antiseptic (fire bioprotection) in two layers.
17. External walls of the house must be treated with 1 layer of fire protection.

Our materials:
1. Beam 200x200 - 316 pieces - 75.85 cubic meters (walls, pediments)
2. Beam 100x200 - 74 pieces - 8.88 cubic meters (beams, of which two are supporting on the 1st floor, on a five-meter span)
3. Beam 50x50 - 56 pieces - 0.75 cubic meters
4. Beam 50x200 - 60 pieces - 3.61 cubic meters (rafters 7 m, with extension)
5. Beam 25x150 - 5.7 cubic meters (2 cubic meters (black floor 1 floor, 2 black floor 2 floor, 1.7 crate).
6. Beam 25x50 - 40 pcs. - 0.3 cubic meters (counter crate).
COST OF WORK???